References
INDUSTRIAL POWER PLANTS, HEATING PLANT
AND BOILER PLANTS
AND BOILER PLANTS
NUMBER OF SELECTED REFERENCES: 20
Page 2 od 4 Back 1 2 3 NextPROJECT:
Preparation of design documents for Power Plant and III Phase "Viskoza", Loznica; and Phase 240 t/h, steam and 30 MW, III phase 30 t/h steam and 25 MW.
Preparation of design documents for Power Plant and III Phase "Viskoza", Loznica; and Phase 240 t/h, steam and 30 MW, III phase 30 t/h steam and 25 MW.
INVESTOR:
“VISKOZA", Loznica
“VISKOZA", Loznica
COUNTRY:
Serbia
Serbia
PROJECT:
Preparation of design documents for extension of Power Plant "Natron", Maglaj, Bosnia and Herzegovina 195 t/h steam and 25 MW.
Preparation of design documents for extension of Power Plant "Natron", Maglaj, Bosnia and Herzegovina 195 t/h steam and 25 MW.
INVESTOR:
“NATRON", Maglaj
“NATRON", Maglaj
COUNTRY:
Bosnia and Hercegovina
Bosnia and Hercegovina
PROJECT:
Preparation of design documents for extension of Power Plant HI "Milan Blagojević", Lučani; 50/64 t/h steam and 5,5 MW.
Preparation of design documents for extension of Power Plant HI "Milan Blagojević", Lučani; 50/64 t/h steam and 5,5 MW.
INVESTOR:
HI “MILAN BLAGOJEVIĆ“, Lučani
HI “MILAN BLAGOJEVIĆ“, Lučani
COUNTRY:
Serbia
Serbia
PROJECT:
Preparation of design documents for Power plant "Incel" Banjaluka, Republic Srpska, Bosnia and Herzegovina, 100 t/h steam and 25 MW.
Preparation of design documents for Power plant "Incel" Banjaluka, Republic Srpska, Bosnia and Herzegovina, 100 t/h steam and 25 MW.
INVESTOR:
“INCEL", Banja Luka
“INCEL", Banja Luka
COUNTRY:
Republic of Srpska, Bosnia and Hercegovina
Republic of Srpska, Bosnia and Hercegovina
PROJECT:
Preparation of design documents for extension of Power Plant for HP "Servo Mihalj", Zrenjanin; turbine implementation 8,5 MW.
Preparation of design documents for extension of Power Plant for HP "Servo Mihalj", Zrenjanin; turbine implementation 8,5 MW.
INVESTOR:
TE “SERVO MIHALJ", Zrenjanin
TE “SERVO MIHALJ", Zrenjanin
COUNTRY:
Serbia
Serbia