LATEST NEWS

March 2020.
Smederevo Steel Mill
HBIS Group Iron&Steel Ongoing Project


The Technical Renovation of the HBIS GROUP Serbia Iron&Steel in Smederevo is one of the most important ongoing projects of Energoprojekt Industrija; therefore, it demands the permanent and complex work of a considerable number of engineers and technicians specializing in all engineering branches on design, technical documentation certification and execution services.
The design review process for the Pusher Furnace Building Permit Design was completed on 25 January 2020. The documentation has been uploaded to the Central Evidence of Unified Procedures for the Issuance of Construction Permits.

The Pusher Furnace Environmental Impact Assessment was submitted to the Ministry and the local authorities in Smederevo for public review on 27 December 2019. The public debate on this topic was held in Smederevo on 22 January 2020. The Building Permit Design documentation for the new Sintering Building is being prepared. It has been agreed with the Investor that the documentation shall be submitted in phases and that the site demands shall be monitored and addressed at weekly meetings of all participants in the project.

March 2020.
EnergoPET

In 2019, Energoprojekt Industrija signed two contracts on the provision of design documentation development services and mediation in obtaining permits and approvals for the planned works, as mentioned in the June 2019 issue of our magazine. In the meantime, the technical documentation for the Production and Commercial Facilities Adaptation has been completed and uploaded to the Central Evidence of Unified Procedures for the Issuance of Construction Permits, so as to obtain permission to commence the execution of works. The development of the Detailed Design is underway. The edited version of the Preliminary Design for the Expansion of the Production Capacities in the Existing Production Plant and Warehouse was uploaded to the Central Evidence of Unified Procedures for the Issuance of Construction Permits on 21 November 2019. All competent holders of public permits have issued their conditions; the issuance of the final Location Conditions and the continuation of activities in compliance with the contractual obligations are pending.

March 2020.
United Nations Development Programme UNDP Serbia
Modernization of Health Care Institutions – Kruševac General Hospital and Dr Vukan Čupić Institute for the Health Care of Mother and Child in Belgrade – Ongoing Project


The trend of improving the provision of medical care by creating modern and efficient healthcare complexes with higher requirements calls for serious professional and overall engagement of all participants in the process, from the Client and users to design engineers and the Contractor, for which the optimization and balancing of the functional and financial demands and the available resources are necessary.

The design brief covers the refurbishment of the constructional elements of the facades and roofs, the replacement of doors and windows with those made of more energy-efficient material, the replacement of lifts and the modernization of all services. Access roads, car parks, greenery and pedestrian areas shall be covered by separate designs. The first phase of technical documentation development for the General Hospital in Kruševac has been completed, i.e., the entire As-Built Design documentation has been submitted to the Investor in both printed and e-form. This service has been invoiced and charged.

The team of designers led by Valentina Vučković Kiš has started working on the next phase –hospital architectural planning and developing the Concept Design for urban development design alongside the preparation of technical documentation for the Concept Design and Preliminary Design, in spite of the unfavourable conditions, since some of the existing facilities do not have a building/operation permit or it was subsequently discovered that they are under the protection of the Institute for the Protection of Cultural Monuments of Serbia. The time necessary to develop this documentation and obtain approvals for the Preliminary Designs shall depend on the fulfilment of conservational conditions which are yet to be defined by the competent institution.

For the purpose of modernizing Dr Vukan Čupić Institute for the Health Care of Mother and Child in Belgrade in accordance with the time schedule specified in the contract, the Investor received the full first-phase documentation of the contract (current condition) in electronic format in December 2019. The priority is to prepare an Energy Efficiency Report with the accompanying documentation related to the Infirmary for hospitalized patients as promptly as possible. Meanwhile, a team of designers of all engineering branches led by Rajko Sević has been preparing the architectural plan and the Concept Design for the urban development design.

March 2020.
Serbia and Montenegro Air Traffic Services SMATSA Ltd Belgrade Contract Activation
SMATSA Annex to Air Traffic Control Centre Building and Control Tower Construction– engineering supervision services


Even though the contract on the engineering supervision services for the works on the construction of the SMATSA Annex with the TWR Building was bilaterally signed in 2019, the Investor introduced the responsible contractor into the project only on 8 January 2020, so the monitoring of the time schedule of works and the engagement of the appointed Energoprojekt Industrija’s design engineers shall be monitored.

March 2020.
Successful Integrated Management System External Audit


On 4 October 2019, the second supervisory audit of the Integrated Management System (IMS) was successfully conducted in Energoprojekt Industrija JSC Belgrade. A team of five YUQS certification body auditors performed an audit of four systems: the Quality Management System in compliance with the SRPS ISO 9001:2015 standard, Environmental Management System in compliance with the SRPS OSO 14001:2015 standard, Occupational Health and Safety Management System in compliance with the SRPS OHSAS 18001:2008 standard and Energy Management System in compliance with the SRPS ISO 50001:2012 standard. We would like to highlight that the scope of certification has been expanded, due to the reformed organization of our business system, whereby the Graphics Department has become a part of Energoprojekt Industrija.